Inclusive Playground for Nyquist Elementary School

Screen Shot 2023-04-19 at 12.15.57 PM.png

Second Draft of Playground

We have decided to go with Landscape Structures.  Our current bid (draft #2) with the PIP Rubber is 381,093.98.  We are meeting with the contractor to find ways to make reductions to this to put it closer to our budget of $200,000.  Currently, the contractor has made a list of possible reductions which would be if it was a community build and with those it would cost 297,344.57.  The PIP Rubber costs around $86,000 of that amount.  We will try to keep this updated as we create new drafts to get it closer to our budget.

Screen Shot 2023-03-19 at 10.40.56 PM.png

Our first presentation was to the School Board.  See our current presentation here: 

playgroundmartycreation.jpeg

This is a computer-generated rendition of our thermometer we created for our school.  Thank you to the Mille Lacs Messenger for recreating this for us and for putting it in the newspaper!

Screen Shot 2023-03-19 at 10.13.39 PM.png

Marty the Playground Moolah Monster

This is our Thermometer for Keeping track of Donations.  We will be keeping this updated as we reach new goals.  Our goal is $200,000, and as of April 21st, have raised $53,750.

playgroundwahkon2.jpeg

Business Letters

We created a business letter to send out to local organizations.  Here is our letter we created: 

Playground (1).jpeg